2 MW wind turbines in Jiangsu Province has been offline
Jiangsu Province, the first 2 MW wind turbines in the September 7, 2010 in East Taiwan, shipped off the assembly line, which shows wind power equipment manufacturing industry in Jiangsu Province, formed a complete industrial chain. Jiangsu Province, the rapid rise of wind generator manufacturing industry, which had been able to mass production blades, control systems, towers and other components, but as a core component of the wind turbine has been imported. Dongtai introduced this year, the domestic wind power generators equipment manufacturer Shanghai Electric Group, the leader in a total investment of 2 billion yuan, mainly developing, producing 2 MW, 3.6 MW of power on land and sea fans. Project on February 2 this year, was started, only 120 days to successfully put into operation. This project a completed, will form a 70-80 kilowatt wind turbine capacity, sales of four billion yuan in
Related Articals
Comments Off